Electricity Upgrade

07/08/2018

Logo

We are back to full operations after an exceptionally busy summer shutdown week where supported by several companies including Northern Powergrid, ESE Engineered Systems, GMC Electrical, Hodgson – Sayers and our own maintenance technicians the power was increased at our laminated production facility by an additional 1000 KVA.

This project was planned 8 months in advance and had to be completed during our 1 week summer shutdown, as part of the project 2 new transformers were installed to support the additional electricity load as well as various new mains switches and DB boards.

This work was carried out to support our new machinery installations as part of on-going investment programme strategy.